On the North End of the Animas River Trail, an Endangered Mouse Helps Set the Schedule

October 8, 2026

The city's Oct. 4 construction report says more vegetation clearing will take place this fall on the west bank of the Animas, across from the trail behind Durango High School, with environmental specialists directing the work. The reason is the timing of the endangered New Mexico meadow jumping mouse. The clearing is meant to keep the mouse from building winter hibernation nests inside the construction zone before the cold sets in. On the east bank, the main trail corridor between 29th Street and Demon Bridge has been open again since Aug. 28.

The two banks show how this part of the trail gets rebuilt. The city budget decides the order of the work. A wet hillside and a small hibernating mammal decide much of the timing.

Where Things Stand the Week of Oct. 5

Piece of the north end Status this fall Source of the date
Main corridor, 29th Street to Demon Bridge Open since Aug. 28, 2026 City of Durango, Aug. 28 notice
Spur trail to Rio Vista Circle Closed for rebuilding, about 2 to 3 months Orange Cone Report, Oct. 4
Demon Bridge Open while crews build abutments for a replacement Orange Cone Report, Oct. 4
New Demon Bridge Installation planned for spring 2027 City of Durango
Rea Trail, soft surface Open between the south end of Riverview Drive and the access corridor linking Rio Vista Circle and north Riverview Drive City of Durango, Aug. 28 notice

Phase 1 started June 8. The 29th Street parking lot served as the staging area, and trail traffic was sent around on a detour along 29th Street, Rio Vista Circle and the Rio Vista spur. That spur used to be the detour. Now it is the part under construction. The city is rebuilding it with better grades, a new surface, drainage work and more trees, and trail users are asked to follow the posted detour signs.

Phase 1 covered clearing, demolition, tree protection, electrical and fiber conduit, poured concrete and landscaping. The conduit work points to the trail lighting in the city's plans. Under the project's design standards, the trail is meant to be at least 10 feet wide, built of concrete instead of the old worn asphalt, with gentler grades, better sightlines on curves, lighting along its length and safety railings where they're needed. The design also calls for a continuous 2-foot soft-surface strip along the edge, which the city notes is popular with trail runners. Those are design specifications. The city's reopening notice doesn't list which of them are already in place.

Why This Stretch Has Always Moved Slowly

The holdups here are older than this year's work. In March 2022, the Durango Herald reported that a plan to replace about 1,800 feet of trail between Rank Park and Demon Bridge had been delayed. The work had been scheduled for late summer 2021, but the city paused it to find out whether construction would disturb jumping mouse habitat.

The ground itself is the reason. Water seeps out of the slope above the trail behind the high school, and Scott McClain, then the city's assistant parks and recreation director, told the Herald that the seeps put that section of trail in the wetland category. Handling the drainage properly meant raising the trail grade and building a structure to carry the seep water under the trail. A higher grade made the project footprint bigger, and a bigger footprint meant the effect on the mouse had to be studied before work could go ahead. Projects in wetlands need approval from the U.S. Army Corps of Engineers. The city's environmental consultant consulted Colorado Parks and Wildlife and Durango wildlife biologist Jennifer Zahratka.

That background explains this fall's notices. The city describes the west bank clearing as required by the project's environmental permits. The permits and the wetland are why the work comes in phases and why each update mentions wildlife.

Why the Clearing Is Happening Now

According to Zahratka, the New Mexico meadow jumping mouse hibernates seven to eight months a year and is one of the smallest mammals that hibernate. Some weigh as little as 20 grams. It has unusually large hind feet, a long prehensile tail and water-resistant fur, and Zahratka said it climbs and swims well in addition to jumping. It was federally listed as endangered in 2014.

The October clearing follows from that long hibernation. If a mouse nests in the work zone this fall, it could stay there for most of the following year, right where crews need to work. The city's Oct. 4 update says the clearing is being done proactively to discourage winter hibernation nests in the project area, under the direction of environmental specialists. Clearing in fall keeps the area free of nests for the spring bridge work.

Zahratka told the Herald that the habitat is about more than the mouse. The riparian strip along the river also supports migratory birds and deer. "Those riparian habitats that they live in give stabilization and help erosion and they help our water clean," she said.

What Spring Brings at Demon Bridge

The abutments going in now will hold a new Demon Bridge, which the city plans to install next spring. The design calls for a wider span with smoother abutments, built high enough to meet waterway freeboard requirements without changing the grade of the nearby railroad crossing. The trail's turn at the east end of the bridge is planned to be wider so the curve is safer, and the connection to the soft-surface Rea Trail will be adjusted as needed. The plans also redesign the steep intersection where the trail meets Rank Park, the Rec Center spur and the railroad crossing, with new striping and signs at the crossing. They add a soft-surface shortcut with boulder steps.

The city hasn't given an exact date beyond "next spring." Elsewhere on the trail, construction has followed the budget year. The Santa Rita North to DoubleTree segment started construction in March 2025 and was scheduled to finish in fall 2025, with F&M Construction as contractor. The Santa Rita South to Nature's Oasis segment is still in the planning stage, and bidding depends on future annual budget allocations. The city says the same thing about the project as a whole. Finishing the remaining sections depends on money set aside year by year.

Race Week Lands on the Same Trail

The trail gets busier on Sunday, Oct. 11, with the first Durango Marathon, Half Marathon and 5K. All three start at Santa Rita Park, 149 S. Camino del Rio. The marathon goes off at 7:30 a.m., the half marathon at 7:45 a.m. and the 5K at 8 a.m. They're run by Black Bear Events, founded by Kaila and Josh Coon. Josh is a former Fort Lewis College cross country coach, and Kaila is a guidance counselor at Durango High School. Race proceeds fund a scholarship managed by the Durango Education Foundation.

The marathon heads north through town on streets and paths and turns around on County Road 250 just past Steven's Creek. It comes back by way of East 32nd Street and East 3rd Avenue, then joins the river trail for the finish at Santa Rita. The 5K is an out-and-back on the river trail from Santa Rita. Roads stay open, and the Herald reports that most of the running will be on wide sidewalks and bike paths. Kaila Coon told the paper that registration was close to 200 runners about a week before the race. Ska Brewing Co. is donating the beer garden at the finish.

That same week, the usual indoor fallback near the Rec Center spur is closed for maintenance:

  • The Durango Community Recreation Center is closed Oct. 11 to 17 and reopens Sunday, Oct. 18, at 10 a.m.
  • The aquatics area is closed Oct. 10 to 18 and reopens Monday, Oct. 19, at 5:45 a.m.

For a stop on North Main near the 29th Street end of the trail, 81301 Coffee House and Roasters is at 3101 Main Ave., Suite 1, and Zia Taqueria is at 2977 Main Ave.

The city posts updated detour maps on its weekly Orange Cone Report, which you can get by email through the NotifyMe system by choosing "City of Durango News Flash." The Rio Vista spur is expected to stay closed into December, and Demon Bridge stays open until the replacement arrives in spring.

Amber Johnson grew up in Durango and has followed projects like this one at the north end of town for years. If you have questions about how trail access, wetlands or wildlife rules affect a property you own or are considering in town, Amber Johnson is glad to talk it through. Let's Connect.

Work With Amber

Get assistance in determining current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.